Research Phase$35,000.00
Design Costs and Simulation Testing$8,800.00
Building Materials$57,000.00
Finishes$28,000.00
Photovoltaic Solar Panels$37,200.00
Hot Water System$5,300.00
Mechanical and Electrical Equipment$11,300.00
Specialties and Appliances$17,000.00
Pre-assembly and Testing in Austin, TX$25,000.00
Transportation to Washington, DC$12,000.00
Transportation back to Austin, TX$12,000.00
Team Travel to Washington, DC$4,200.00
Team Per Diem Expenses in Washington, DC$5,400.00
Team Lodging in Washington, DC$8,200.00
Print Material$4,500.00
DVD Documentation$6,000.00
Electric Vehicle$7,400.00
Uploading and Loading$10,300.00
Publicity$2,000.00
Miscellaneous Expenses$5,000.00
Contingency$30,200.00
Inflation$9,000.00
Total$340,800.00